Pre Sheet Rock Meeting

From the beginning, we have been told that there are three meeting milestones in the construction of our house.  The first was the red line meeting, then the pre sheet rock meeting, and finally the final walk thru.

We received and email from Todd informing us that our house had been inspected by a third party inspector and crews were working through the punch list in anticipation of the city inspector coming out at the end of this week.  He also wanted to schedule our pre sheet rock meeting, which we scheduled for last Tuesday.

At the meeting Todd made sure that all the major changes (extra bathroom, built in patio) were present, which they were.  I cannot imagine what kind of delays would occur if something like an extra bathroom was missing.

Then, we went through all the electrical options.   We had him change the location of a few of the outlets and other minor changes.

Then, we asked him the million dollar question....when will we close?  He said that our house was a priority since we had so many delays in the beginning and expects us to close mid September.  So, we put in our 60 day notice -- the pressure is on!

He told us that we can expect the city inspectors to come out at the end of this week (today), insulation should go in during the early part of next week and then we would have sheet rock in the latter part of next week.  He also said we could have brick and stone delivered and installed any day now.  So far he has been pretty accurate, so we are hopeful!